Client at a glance

Client
Lend Lease and Sydney Airport Corporation Ltd.
Location
Terminal 1 Northern Multi Storey Car Park
Completion date
Dec 2017
System size
550kW
Project type
Solar Car Park (Design and Construct)
Connection Type
415 volts, behind the meter
In line with Sydney Airport’s Sustainability Strategy, Autonomous Energy has delivered a 550kW solar car park shading project at Sydney International Airport’s (T1) Northern Multi Storey Car Park. Working in conjunction with Lend Lease, we have delivered a fully integrated solar PV system without compromising on car park spaces and functionality.
 
Installed on the 12th storey of the car park, the design and high-quality installation of this innovative system supports Sydney Airport’s commitment to continual improvement in environmental management. Our solution involved a custom designed and built structure that resulted in the ability to safely install a much larger system than would be possible with an ‘off-the-shelf’ solution. This project demonstrates our capability in both designing and installing solar in unique and challenging areas without compromising on safety and performance.
 
We successfully managed all aspects of this solar PV project while maintaining the high safety standards of Lend Lease, Australia’s leading construction company. This project is the latest in a long line of successful car park shading projects delivered by Autonomous Energy.

Autonomous Energy solution

  • Designed in-house by our experienced and innovative solar PV engineers
  • Largest span between columns of any solar car park in Australia
  • 1,800 special low reflectivity panels installed in 4 weeks by our in-house installation team
  • 835MWh produced per year
  • Custom-designed and locally manufactured steel structure
  • Effectively managed the difficulties of transporting and installing equipment on the 12th storey of a car park at a busy live site
  • In total, 45 tonnes of steel and 25.2 tonnes of aluminium installed
  • Integrated LED car park lighting
  • Accreditation of the system with the Clean Energy Regulator to produce Large Scale Generation Certificates

Client at a glance

Client
Lend Lease and Sydney Airport Corporation Ltd.
Location
Terminal 1 Northern Multi Storey Car Park
Completion date
Dec 2017
System size
550kW
Project type
Solar Car Park (Design and Construct)
Connection Type
415 volts, behind the meter

Questions? Call us on 1800 314 759

We'd love to hear from you